The major framing is coming to an end by Friday of this week. They are finishing up enclosing the roof with that reflective plywood sheathing, and finishing up the soffets. The windows are scheduled to arrive tomorrow and those should go in the same day. That completes everything needed for the next inspection, "Nail Pattern" I guess they look to make sure everything is nailed together correctly.
It is really starting to look like the plans. Glad they are almost done framing, I am getting really tired of writing checks for lumber.
They used this soffet material all around the house.
Looking up at that plywood sheathing they used on the roof that has a reflective foil covered side.
Standing in Foyer looking upstairs. There will be railings along this upstairs hallway. As soon as the nail pattern inspection is complete, the roofers come in and put on the finish roof to protect the wood, and the electricians, plumbers, and HVAC people come in and do their rough-ins.